We’re getting there …

Since New Year, there has been lots of progress:

  • Floor has been screeded
  • Passmores have finished their work, fitting internal doors etc
  • Ceilings have all been fitted by a contractor
  • 40% of the 100 or so panels of plasterboard have been fitted by us, at three all-day working parties – it’s got a lot of walls, especially when you have to fit to both sides of the internal partitions!

Imminent works include rainwater drainage and landscaping starting on Friday 1st March; flooring has been ordered and will be fitted to kitchen and toilets week beginning 11th March – we have to finish painting walls and ceilings in those rooms by then. The electricity will be reconnected on 6/7th March. Lots to do!